Development plans for railway under review

July 29, 2011 by  
Filed under News

Letter from Lee Seng Lai Director Land Operations (Private) Division Singapore Land Authority and Tan See Nin Director (Physical Planning) Urban Redevelopment Authority, TODAY, 29 Jul 2011.

We refer to the letter from Mr Liew Kai Khiun, “A temporary park connector?” (July 21)

As agreed with Malaysia, Singapore has to remove the railway tracks and ancillary structures along the former KTM railway line, and hand them over to Malaysia by Dec 31.

This is a very tight timeline, given the extensive work required: The Singapore Land Authority (SLA) has to remove 26km of railway tracks in five months. The SLA started removal works on July 18.

Read more

Source: TODAY